OSAF Status Overview, Dec 2
December 2nd, 2005 at 12:44 pm (2 years, 7 months ago) by Lisa Dusseault under Chandler Desktop Development, Chandler Server DevelopmentApologies for the late and less-structured status overview this week. I’ll confine this to what people sent me or posted on the Wiki for recent status.
- Operations meeting minutes
- Engineering Meeting minutes (milestone and release planning)
- Design meeting notes
- QA Status
- Applications Team meeting minutes
- Services and Dev Platform meeting minutes
- Cosmo: “0.2.4 is *just* about ready to tag and roll. there’s only remaining issue: a KEI internal project needs a signup operation added to CMP. i expect that to be done and 0.2.4 to be handed off to QA by the end of day monday.” — BCM
- Scooby:
From Bobby Rullo, Scooby progress:
- removal of events is now asychronous
- localization framework in place
- button drawing client side library started
- client keeps server side session alive by “pinging” every time the user does something on the client side
- Event detail area moved to the bottom of the page
- Resizable area for the all day events started - the same resizable widget will be used for the sidebar later.
- Started work on “all day” support
- Started work on caldav4j
Scooby plans
- finish all day support, as well as support for different event types (all day, any time, point in time)
- drop LocalScoobyService, add initial support for Cosmo instead
IT Status from Jared
- Progress: Full NMAP reconciliation complete. LPFI community technology selected. VPN plan complete, prototype proceeding. KEI mailman instance created. OSAF QA intern set-up.
- Plans: Rework cosmo-demo for new Java 1.5 requirements. Build new colo box for LPFI web site hosting. Close KEI sysadmin hire by mid-December. Review bandwidth shaping progress.
- Personnel: Hire KEI sysadmin and OSAF IT Intern. Jared and Chris have some late December vacation plans.