OSAF Status Overview, Oct 25
October 25th, 2005 at 2:36 pm (2 years, 8 months ago) by Lisa Dusseault under Chandler Desktop Development, Chandler Server DevelopmentHighlights
- Chandler: Milestone 6 released, which is feature complete for 0.6 (Scorecard). 210 bugs targetted for final release.
- Progress: Beginning specs for 0.7 (Free-busy viewing first draft, thoughts on markup bar and table cleanup), images for vision and design docs/presentations
- Plans: More spec work, more ACL, triage and free-busy design work
- Plan : Continue making progress on 0.6 bugs
- Progress : Going toward zero, glide path (fix rate - find rate) continue to be good
- Problems : Unclear how we can declare perf bugs “fixed”, need clearer guidelines
Services and Dev Platform
- Progress: Performance: any user action when a large calendar is loaded is much faster. E.g. switching a view.
- Plans: Work on 64 bugs targetted to 0.6
Build and QA
- Progress: Tinderbox perf info — many improvements (still ongoing)
- Plans: Fix build bugs in 0.6 list.
Cosmo and Scooby
- Progress: Week view now has viewing, saving and deleting events from the server. Cosmo 0.3 begun with some bug fixes.
- Plans: Authentication system, multiple user support work. Navigation between weeks. Minical. Recurrence. Make build system more friendly. Cosmo 0.3 feature development.
- Progress: pushed off Bugzilla enhancement projects. VNC server for remote demo viewing been tested. Installed KVM at ISC.
- Plans:
- Personnel: Hiring junior helpdesk person
Community
- Progress: Educause panel and demo last week showed Chandler subscribing to calendars on Cosmo, RPI and Oracle servers. Chandler branding work progress (chose icon).
- Plans: Refactor OSAF Web site (move some pages to wiki, remove others, or update). Making PyCon presentation proposals by Oct 31.